Work Performed
Schedule 1 included 1,475 LF of 8” PVC water main that replaced 4” AC. Schedule 2 included 1,275 LF of 8” PVC water main that replaced 6” and 4” CIP and 6” AC. Schedules 1, 2 and 3 included 4 horizontal directional drills of 120 LF each installation of 8” carrier pipe. Schedule 6 included 1,100 LF of 8” PVC Water Main.

Partner with Us

If you’re looking for a trusted partner to bring your infrastructure project to life, look no further than Western Municipal Construction. Our track record of success, combined with our unwavering commitment to quality and innovation, makes us the ideal choice for your next project. Contact us today to learn more about our services and how we can help you achieve your goals.