Thayne WY Oct 2019
Contract Amount
$918,314.50
Work Performed
Construct 300,000 gallon concrete water tank. Installation of 680LF of 10″ HDPE water pipe plus all site work for new road and slope to tank. Work included sandblasting, coating of existing tank, and modification of internal overflow.